Work continued on this popular, well-used riverside path.
Today Jerry, Graham and Jak were out working on revetments to hold the path edge in place and limit further damage as well as protecting walkers from the steep slope leading to the river.
![]() |
Location of work marked in turquoise |
Revetments were installed and backfilled. The path was also widened and a minor diversion created to guide walkers up to the main path and away from the very narrow, slippery secondary path.
![]() |
Timber in place |
![]() |
Back-filled |
![]() |
Diversion! |
![]() |
Full stretch of revetment |
A further section of path was widened.
![]() |
Path widened |
This work was funded by Calderdale Highways
For more details
Follow the CROWS https://communityrightsofwayservice.blogspot.com/
For further information about CROWS follow the link.