Ian V, Linda H and Stella continued the work on upgrades to the Pennine Way.  We constructed a boardwalk to meet a stile and thus allow walkers to remain dry and clean above a tricky patch which in wet weather is a quagmire.

This work is funded by Natural England and Calderdale Highways.

The problem is at the south end of the red line


First we have to carry timber and tools to the site

Heavy!

Ready to roll....


And this is the patch we need to bridge

A lot of the time in constructing a boardwalk is spent choosing the best position and getting levels and angles right.  

The bearers must be level...

...and so must the stringers





When the position is right and the structure braced at each end you can put the stobs in.....

...first making a hole with the bar and then banging in the stobs and nailing them to the stringers


Then very quickly you can lay and nail the treads and add some staples for grip.



,
And hey presto!

The job's a good'un!



 