Ginny, Mo, Stella and Rich tackled a cluster of jobs on a path from Luddenden Beck up to South Ive House.

A path with several different surfaces and problems!

Stella and Mo rescued a fallen waymark post and reinstalled it. 

Further down the four of us pondered how we could deal with a very awkward stile. 

We agreed the answer is that it needs a complete rebuild!

Further down, we did a bit of bramble cutting back, then moved down to a very squelchy stream-side path.

Mulch scraped off, water channelled and stepping stones placed

The next job was to rescue a bridge which had become clogged and which was in danger of being washed away.


All cleared but we need to keep an eye on it.

Finally, we dealt with a tree that had fallen over the path and looked at a section of pitched stone path that had been washed out some time ago. Unfortunately there is no sign of the stone so it is too difficult job to tackle. 