Wednesday, 4 March 2015

Location : Todmorden Moor above Shepherd's Rest Radical eTrail
CROWS : Richard J, Gerald, Dick, Frank, Bernard, Fred and Terry
Tasks : Continuation of last weeks work on the revetment and drainage on the path


 Bernard and Frank fitted the extra board on top of those done last week and we filled the path with broken rocks to give the banking stability and drainage.






 Turn-byes were created at both ends to help the drain the water which was coming from the banking above.






 We worked from the summit of the path downwards dealing with any drainage issues we found.


 The other group of Dick, Fred, Gerald and Richard J started doing the same from the bottom of the path.


 A number of the turn-byes had not been cleared for a number of years.






 The final task was to clear out a drainage channel to the side of the main path where three streams of water were diverted into one.